The project at the Northtec Bristol facility in Bristol, PA, involved installing a 1250kW diesel standby generator for backup power. The Emtec team conducted site survey(s), prepared design documents, and design during construction support. Emtec also provided the foundation plan for the generator enclosure.
Emtec Consulting Engineers supported the bidding process, walk-throughs, value engineering, and contractor selection recommendations. During construction, we managed construction administration tasks, providing field observations, punch list, and project closeout documentation to confirm the generator system was fully operational and compliant.